Germany behind schedule on wind energy rollout: study

Germany behind schedule on wind energy rollout: study

The German Wind Energy Association said 331 wind power stations had been built in Europe's top economy since January with a capacity of 1.57 gigawatts
The German Wind Energy Association said 331 wind power stations had been built in Europe's top economy since January with a capacity of 1.57 gigawatts. Photo: Ina FASSBENDER / AFP/File
Source: AFP

PAY ATTENTION: Be the first to follow YEN.com.gh on Threads! Click here!

Germany has made strides in expanding its onshore wind power capabilities this year but needs to pick up the pace to meet key targets for the decade, a sector study said Tuesday.

The German Wind Energy Association said 331 wind power stations had been built in Europe's top economy since January with a capacity of 1.57 gigawatts (GW).

The findings of an analysis carried out with the VDMA association representing the power and heat generation sector said the 2023 activity marked an acceleration on the previous year, and could total up to 3.2 GW by the end of December.

However, this expansion is still far from meeting the requirements to reach the target of 115 GW installed by 2030, with the existing total now approaching just 60 GW.

Almost doubling this figure would require an expansion of 10 GW every year from 2025 onwards.

Read also

Spain PM fails to get vote boost from economy

At the current rate, "the targets will be missed", said VDMA managing director Dennis Rendschmidt.

The planning and approval procedures for wind power plants can take 24.5 months on average which together with logistical hurdles are a drag on development, the study found.

The sector associations said they hoped a series of recent regulatory measures to cut red tape would soon take effect.

However, political resistance to turbines from local communities poses a further obstacle, with far more permits issued in the north than in the south of the country.

Chancellor Olaf Scholz's coalition government has set a target of allocating at least 1.4 percent of the country's surface area to the installation of wind power stations by 2027, and at least two percent by 2032, compared to 0.7 percent currently.

It has also pledged to produce 80 percent of electricity from renewable sources by 2030.

Read also

Ericsson and Nokia feel squeeze of interest rates hikes

Last week Germany auctioned off rights to build offshore wind power plants for the first time, raising 12.6 billion euros ($14 billion) from the winning bids from energy giants BP and TotalEnergies.

New feature: Сheck out news that is picked for YOU ➡️ click on “Recommended for you” and enjoy!

Source: AFP

Authors:
AFP avatar

AFP AFP text, photo, graphic, audio or video material shall not be published, broadcast, rewritten for broadcast or publication or redistributed directly or indirectly in any medium. AFP news material may not be stored in whole or in part in a computer or otherwise except for personal and non-commercial use. AFP will not be held liable for any delays, inaccuracies, errors or omissions in any AFP news material or in transmission or delivery of all or any part thereof or for any damages whatsoever. As a newswire service, AFP does not obtain releases from subjects, individuals, groups or entities contained in its photographs, videos, graphics or quoted in its texts. Further, no clearance is obtained from the owners of any trademarks or copyrighted materials whose marks and materials are included in AFP material. Therefore you will be solely responsible for obtaining any and all necessary releases from whatever individuals and/or entities necessary for any uses of AFP material.